Recovering Unabsorbed Home Office Overhead Using the Eichleay Formula

By Timothy Sullivan on November 20, 2006
Posted in Contract Performance Issues

The Armed Services Board of Contract Appeals recently reiterated the requirements a contractor must meet in order to recover unabsorbed home office overhead using the Eichleay Formula.  In Kato Corporation, ASBCA No. 51462, the Board held that a contractor must establish three elements to successfully maintain a claim for recovery of its…

Stay Connected

RSS Twitter LinkedIn Facebook

Subscribe to this blog

Topics

Blog Authors Show/Hide

  • Ryan Boonstra
  • Christopher D. Carusone
  • Jeffrey E. Jakob
  • Casey J. McKinnon
  • Michael H. Payne
  • Cohen Seglias
  • Stephen D. Tobin

Archives

Cohen Seglias Blogs

  • A Closer Look: Internal Investigations

Resources

  • Federal Business Opportunities
  • Federal Contracting Database

Recent Updates

  • The Percentages Favor Settlement of Claims and Appeals
  • Recent Decision Highlights the Potential Pitfalls in General Releases
  • The Sovereign Acts Doctrine Strikes Back: COVID Costs Are Its Latest Victim
  • Haven’t Been Paid? Preserve Your Rights Under the Miller Act
  • Settlement Strategy Is More Important Than Litigation Strategy

Federal Construction Contracting Blog

Cohen Seglias Pallas Greenhall & Furman PC logo
RSS Twitter LinkedIn Facebook
DisclaimerPrivacy Policy
Copyright © 2022, Cohen Seglias Pallas Greenhall & Furman PC. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo