Recovering Unabsorbed Home Office Overhead Using the Eichleay Formula

By Timothy Sullivan on November 20, 2006
Posted in Contract Performance Issues

The Armed Services Board of Contract Appeals recently reiterated the requirements a contractor must meet in order to recover unabsorbed home office overhead using the Eichleay Formula.  In Kato Corporation, ASBCA No. 51462, the Board held that a contractor must establish three elements to successfully maintain a claim for recovery of its…

Stay Connected

RSS Twitter LinkedIn Facebook

Subscribe to this blog

Topics

Blog Authors Show/Hide

  • oliviapariskornilowicz
  • Ryan Boonstra
  • Christopher D. Carusone
  • Jeffrey E. Jakob
  • Casey J. McKinnon
  • Michael H. Payne
  • David C. Petrone
  • Cohen Seglias
  • Stephen D. Tobin

Archives

Resources

  • Federal Business Opportunities
  • Federal Contracting Database

Recent Updates

  • ASBCA Says “Not So Fast” to Contractors Seeking Relief from Pandemic Impacts
  • OFCCP Issues September 19 Deadline for Federal Contractors to Object to Disclosure of EEO-1 Data
  • Don’t You Forget About Me: DOL’s Proposed Rule on the Right of First Refusal in Service Contracts
  • Recovering Field Overhead Expenses
  • The Percentages Favor Settlement of Claims and Appeals

Federal Construction Contracting Blog

Cohen Seglias Pallas Greenhall & Furman PC logo
RSS Twitter LinkedIn Facebook
DisclaimerPrivacy Policy
Copyright © 2023, Cohen Seglias Pallas Greenhall & Furman PC. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo