It is Difficult to Successfully Challenge an Agency's Past Performance and Risk Evaluation

This article describes a GAO decision that highlights how difficult it is to prevail on a protest that challenges an agency’s rating of a proposal where the protest is not supported by anything more than a difference of opinion as to how much weight, or what score, should be assigned to a particular evaluation factor. Absent a showing that there was no rational basis for an agency’s evaluation, contractors should not expect the GAO to overturn an evaluation.

The GAO published a decision today that was originally issued on July 19, 2006, but delayed in being made public because of the need for redactions.  The case involved a protest by East-West Industries, Inc. against the award of a contract to Regent Manufacturing, Inc.   The solicitation was issued under request for proposals (RFP) No. FA8518-04-R-70801, advertised by the Department of the Air Force for multi-aircraft canopy cranes (MACC). East-West challenged the past performance and risk evaluations of its and Regent’s proposals. The protest was denied.

In its decision, East-West Industries, Inc. , B-297391.2; B-297391.3, the GAO stated that in reviewing a protest of an agency’s proposal evaluation, “our review is confined to determining whether the evaluation was reasonable and consistent with the terms of the solicitation and applicable statutes and regulations.” The GAO found that the evaluation of protester’s proposal under the past performance evaluation factor was unobjectionable where the agency reasonably concluded that only one of four prior contracts was of a magnitude and complexity essentially the same as the solicitation’s, and thus met the solicitation’s definition of very relevant. Since only one contract was rated very relevant and the protester received exceptional performance ratings under only two of its three relevant contracts, the GAO determined that the agency reasonably concluded that East-West’s performance record warranted assigning the firm a very good/significant confidence rating based on there being little doubt--rather than no doubt--as to its successful performance.

The protester also argued that the agency’s risk evaluation for Regent’s proposal was flawed.  Specifically, East-West asserted that Regent’s [deleted] design, and prior delivery and safety/quality problems, indicated a moderate to high risk of increased costs, degradation of performance, and schedule disruption. The GAO disagreed and found that the evaluation of the awardee’s past performance and risk was reasonable, notwithstanding protester’s identification of alleged quality, safety, and delivery issues, where contracting officials did not have personal knowledge of majority of the issues, and fully considered those of which they were aware in finding no negative impact on awardee’s past performance rating.

In an interesting side comment that GAO stated it has recognized that in certain limited circumstances an agency evaluating an offeror’s proposal has an obligation (as opposed to the discretion) to consider “outside information” bearing on the offeror’s proposal, where the information in question was “simply too close at hand to require offerors to shoulder the inequities that spring from an agency’s failure to obtain, and consider this information.”  International Bus. Sys., Inc., B-275554, Mar. 3, 1997, 97-1 CPD para. 114 at 5.  In those narrow instances where the GAO has applied the “too close at hand” principle, it has “required the protester to demonstrate that the outside information bearing on the offeror’s proposal was not just known by the agency generally but, rather, was known to the agency employees involved in the source selection process.” The GAO found that no such “outside information” was available to the agency in this case, however.

GAO Recommends Navy Return To Square One in Award of Billion Dollar Contracts

The Navy recently awarded three cost-plus-award-fee, indefinite-delivery/indefinite-quantity (ID/IQ) contracts to Fluor International, Inc., URS-IAP, LLC (a joint venture of URS Corporation and IAP Worldwide Services, Inc.) and Atlantic Contingency Constructors, LLC (a limited liability company managed by The Shaw Group) for global contingency construction. Each contract was for a base year with four one year options, and the value of each contract was approximately one billion dollars. The contractors were to provide construction and related engineering services in response to war fighting needs, global natural disasters, and humanitarian assistance.

The awards were made following a "best value" evaluation based on experience, past performance, contingency planning, management, small business utilization, and cost. Non-cost factors were considered more important than cost. A disappointed offeror, Kellogg Brown & Root Services, Inc. (“KBR”), filed a GAO protest asserting that the Navy misevaluated the proposals under technical and cost factors. The GAO agreed and issued a decision sustaining the protest.

In a rather complicated and detailed analysis, the GAO determined that the cost comparison performed by the Navy was flawed because the agency did not perform a reasonable cost realism evaluation. Specifically, the Navy’s evaluators deleted a certain element of cost from ACC’s proposed indirect costs because other offerors had accounted for the same element as a direct cost. KBR argued that if this adjustment had not been made, KBR’s evaluated cost would have been lower than ACC’s. The protester went on to argue that it was unreasonable for the agency to make an adjustment to ACC’s costs when it was apparent that there were other instances where the offerors had treated costs differently for accounting purposes that were not accounted for in the cost evaluation.  Given the multiple accounting variances among the offerors, the agency’s “singling out” of certain ACC costs to adjust from indirect costs to direct costs was unreasonable, according to KBR, and represented unequal treatment.  Significantly, the GAO commented that “The agency has offered no substantive response to this KBR contention, which, based on this record, appears to have merit.” The GAO concluded that the agency’s adjustment to ACC’s proposal was unreasonable and prejudicial to KBR because it resulted in ACC’s proposal being evaluated as having a lower cost than KBR’s.

In another aspect of this protest, KBR contended that the agency misevaluated its proposal and the proposals of URS and ACC under many of the technical factors.  In particular, KBR asserted that the agency overlooked a number of strengths, and assessed a number of weaknesses that were unreasonable with regard to the contingency plan factor.  The Navy responded in cursory fashion that KBR’s proposal was “more general” and provided “limited details,” and contended that the protester’s arguments reflect only “mere disagreement” with the agency.  The GAO disagreed and concluded that “Our review of the record shows more than “mere disagreement.”  The protest was therefore sustained because “the record does not, on its face, support the agency’s ratings, and the agency has otherwise failed to explain the difference in ratings.”

The GAO recommended that the Navy reevaluate the proposals, conduct discussions if necessary, and make a new source selection decision. If based on this new evaluation, the agency determines that one or more of the awardees are no longer in line for award, the GAO recommended that the agency should terminate the awardees’ contracts and make awards consistent with the new selection decision.

This decision is important because it represents a departure from the GAO’s frequent reluctance to look behind the discretion of source selection officials, as long as some justification is provided for their decisions. Given the very large and important defense contractors involved, and the subject matter of the procurement, it will be interesting to see if the Navy complies with the GAO's recommendations, and whether there is ultimately a new list of awardees. One thing is certain; with this much money involved additional challenges to the procurement are likely to arise. See Kellogg Brown & Root Services, Inc., B-298694; B-298694.2; B-298694.3, November 16, 2006.