Can a Contractor ever ask the Government for Attorney's Fees?

By: Edward T. DeLisle

We are frequently asked whether attorneys fees are recoverable as part of the federal claims procedure. The answer is sometimes. A case just decided by the Court of Appeals for the Federal Circuit assists in explaining when such a recovery is possible.

In Tip Top Construction v. Donahue, the United States Postal Service required a contractor to perform additional work to complete an air conditioning repair project in the Virgin Islands. While it approved a change order to perform the additional work, the contractor incurred other additional costs, including attorneys fees, to convince the USPS to accept its request for additional money. Those monies were submitted in the form of a claim and denied.

The U.S. Postal Service Board of Contract Appeals upheld the denial stating that the costs included in the claim "had nothing to do with the performance of the changed work or genuine contract administration." The Federal Circuit disagreed.

The Federal Circuit took the position that the monies included in the claim reasonably flowed from negotiations associated with the change order process. This conclusion was important, for the Federal Circuit framed the issue as follows: "If a contractor incurred the cost for the genuine purpose of materially furthering the negotiating process, such cost should normally be a contract administration cost allowable under FAR 31.205-33, even if negotiation eventually fails and a CDA claim is later submitted." Here, the facts revealed that the parties were, in fact, making attempts to negotiate an amicable resolution regarding price for a number of months prior to submission of the claim. Consultants and attorneys were used by the contractor to assist it in its presentation to the Postal Service. Because the evidence suggested that the contractor's underlying purpose was to resolve the dispute, the Federal Circuit held that these costs were recoverable.

Tip Top illustrates the fine line one must walk when it comes to the collection of attorneys fees. Certainly, once an actual claim is submitted by a contractor, there can be no expectation to collect fees from that point forward. The dispute has traveled too far down the road of dispute resolution. Prior to that point, however, if a contractor can prove that the costs incurred for counsel stemmed from a desire to negotiate an amicable resolution to a change order dispute, recovery of fees is possible.

Edward T. DeLisle is a Partner in the firm and a member of the Federal Contracting Practice Group.

When Certifying a Claim is Required, Do Yourself a Favor...Don't be Creative

By: Edward T. DeLisle & Maria L. Panichelli

When it comes to problem-solving, we are often encouraged to “think outside the box.” The idea is to be creative; to look beyond the norm. Well, when it comes to certifying a claim, you’re probably better off simply doing what the FAR tells you to do. The Civilian Board of Contract Appeals made this point clear in URS Energy & Construction v. Dept. of Energy.

As most contractors are aware, all claims over $100,000 must be accompanied by a certification. FAR § 33.207(a). FAR §33.207(c) sets forth the exact language that such a certification must contain. That language is as follows:

“I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the Government is liable; and that I am duly authorized to certify on behalf of the Contractor.”

In URS Energy & Construction, the contractor certified its claim to the Department of Energy using language that differed from the FAR:

“I certify that this invoice is correct and in accordance with the terms of the contract and that the costs incurred herein have been incurred, represent the payments made by the Contractor except as otherwise authorized in the payments provision of the contract, and properly reflect the work performed.”

The government asked the CBCA to dismiss the contractor’s claim on the basis that the certification used was defective, thereby depriving the CBCA of subject matter jurisdiction over the claim.

In ruling on the motion, the CBCA noted that “technical” defects in a certification can be cured; however, “[i]f the certification is made with intentional, reckless or negligent disregard for the applicable regulation, it is not correctable.” The CBCA found that the contractor’s claim was made with “intentional, reckless or negligent disregard” because the contractor wholly failed to include a certification that “the claim is made in good faith,” or that “the supporting data [was] accurate and complete to the best of [the contractor’s] knowledge and belief.” Moreover, the certification failed to include a statement that the person signing the certification was duly authorized to certify the claim on behalf of the contractor. Accordingly, the CBCA dismissed the case.

The lesson: certifying a claim is not the time to be creative. The language in FAR §33.207(c) must be reviewed carefully and, unless there is very good reason to diverge from what is identified therein, you are better off simply incorporating it verbatim into your claim. If you cannot attest to those issues required by the FAR, you should think twice about filing a claim at all, for submitting a defective certification, which is true, is far better than submitting a false certification. That is something you should avoid at all costs.

Edward T. DeLisle is a Partner in the firm and a member of the Federal Contracting Practice Group. Maria L. Panichelli is an Associate in the firm’s Federal Practice Group.

Federal Construction Contract Claims Must be Evaluated Fairly

By: Michael H. Payne

The growth of contracting by negotiation or “best value” procurement, has had a chilling effect on the submission of claims by construction contractors. There seems to be a growing fear that claims are frowned upon by contracting officers and that they will be counted against a contractor during future proposal evaluations. This fear, in my opinion, is misplaced provided that the claims are not frivolous and are technically and legally supported.

The Contract Disputes Act of 1978, 41 U.S.C. § 601 et. seq., requires contractors to certify that claims in excess of $100,000 are “made in good faith,” that all “supporting data are accurate and complete to the best of [the contractor's] knowledge and belief,” and that the amount requested “accurately reflects the contract adjustment for which the contractor believes the government is liable.” 41 U.S.C. § 605(c)(1). A contractor who is willing to make that certification should not be denied the opportunity to recover the additional costs, or time, that the contract and the law specifically allow. There are a number of clauses in federal construction contracts, including “Changes” (FAR 52.243-4), “Differing Site Conditions” (FAR 52.236-2) “Suspension of Work” (FAR 52.242-14) “Termination for Convenience” (FAR 52.249-2), etc., that afford contractors with the right to seek an equitable adjustment to the contract. These clauses apply to sealed bidding and negotiated procurements alike, and the fear of retribution on proposal evaluations should not be used to deny contractors the very rights that the contract and the law provide.

It is also important to note that contracting officer’s are required to deal with claims fairly, and there is a duty of good faith and fair dealing in government contracting. As the U.S. Court of Federal Claim noted in Lavezzo v. United States, a contracting officer is obligated to “put his own mind to the problems and render his own decisions.” Such decisions must be “personal [and] independent,” and “even the appearance of coercion [must] be avoided.” 74 Fed.Cl. 502, 509 (2006). In addition, a Contracting Officer's outright denial of meritorious contractor claims to gain some advantage over the contractor will not be condoned by the Court. In other words, a contracting officer's review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor. Moreland Corp. v. U.S., 76 Fed.Cl. 268 (2007). Contractors are legally entitled to submit claims, to have those claims fairly and impartially reviewed, and contractors are entitled to do so without fear of the impact on future source selections.

Michael H. Payne is the Chairman of the firm's Federal Practice Group and, together with other experienced members of the group, frequently advises contractors on federal contracting matters, including teaming arrangements, negotiated procurements, bid protests, claims, and appeals.

New DFARS Provision Has a "Chilling Effect" on Claims

One of the byproducts of the recent use of negotiated procurements under FAR, Part 15, has been the concern, on the part of contractors, that the submission of claims will be a negative factor during the evaluation process on a Request for Proposals.  While we can certainly understand that a contractor who has a history of filing frivolous claims might deserve to be downgraded, we see no valid reason for the government to assign a lower rating to a contractor who has filed meritorious, or good faith, claims in the past.

On February 12, 2006, a provision was added to the Defense Federal Acquisition Regulation Supplement (DFARS) dealing with the review of claims that we find very disturbing.  Under DFARS Subpart 233.2, Disputes and Appeals, Paragraph 233.10, “Contracting Officer’s Authority,” there is a reference to a new “PGI” (Procedures. Guidance and Information). The new guidance states that “When it would be helpful in reviewing the current claim, the contracting officer should get information on claims previously filed by the contractor.  Such information may provide a historical perspective of the nature and accuracy of the claims submitted by the contractor and how they were settled.  Potential sources for the information include the contracting activity’s office of legal counsel, other contracting activities, and the Defense Contract Audit Agency.”

We believe that each claim should stand on its own merits.  Each claim is different and is the result of a different contract, a different set of facts, and is ultimately decided by a different set of legal principles.  In addition, the Contract Disputes Act of 1978 gives contractors the right to file claims.  It seems to us that “guidance” that could potentially penalize contractors for filing claims is most inappropriate.

PGI – Procedures, Guidance and Information

Description: Procedures, Guidance, and Information (PGI) is a companion resource to the Defense Federal Acquisition Regulations Supplement (DFARS). The PGI is a web-based tool to simply and rapidly access guidance and information relevant to FAR and DFARS topics. The PGI is the result of the DFARS Transformation chartered by the Under Secretary of Defense for Acquisition, Technology and Logistics. It contains both mandatory and non-mandatory internal DoD procedures, guidance, and supplemental information. This brief module will present basic information about the DFARS Procedures, Guidance, and Information.