The Right of Contractors to Challenge Unfair Performance Evaluations is Further Expanded by the U.S Court of Federal Claims

We recently reported (see our earlier blog article) the decision of the United States Court of Federal Claims in BLR Group of America, Inc. v. United States, issued on November 25, 2008, in which the Court opened the door to contractor challenges of unfair or incorrect performance evaluations.  Coming literally on the heels of the BLR case, the Court issued another decision on December 9, 2008, Todd Construction Co., Inc. v. United States, denying a government motion to dismiss and holding that the Court had the jurisdiction to consider a challenge to a contracting officer’s decision regarding a contractor’s performance evaluation.  The Court held that Todd had submitted a “claim” within the meaning of the Contract Disputes Act of 1978 because, on March 22, 2006, the Government issued its proposed final evaluations of Todd’s work, and on April 20, 2006, Todd submitted its comments protesting those evaluations.  The Government issued final evaluations on July 21, 2006, and Todd submitted both a claim and a supplemental claim to the Department of the Army, asserting regulatory violations in the preparation of the evaluations and lack of factual accuracy. On April 25, 2007, the contracting officer wrote to Todd, indicating the letter “serves as my final decision regarding your performance on the above Task Order” with a subject line “Final Contracting Officer Decision.”  Based upon these facts, the Court held that “this is a final decision of the contracting officer upon a written demand.”

In 2003, Todd Construction received two task orders from the United States Army Corps of engineers (“Corps”) for roof repair of buildings at the Seymour Johnson Air Force Base in North Carolina, and the work was completed in September of 2005. On March 26, 2006, the Corps issued proposed final evaluations rating Todd’s overall performance on the work as unsatisfactory.  Todd submitted comments to the contracting officer explaining why, in its view, those ratings were unmerited, but the contracting officer nonetheless issued final unfavorable evaluations on July 23, 2006.  In August of 2006, Todd appealed the contracting officer’s decision to Ms. Rita Miles of the Department of the Army, alleging that the Government (1) violated the applicable performance review procedures set forth in Army Corps of Engineers Regulation 415-1-17 and (2) arbitrarily issued evaluations unsupported by the facts.  Ms. Miles apparently provided some documents to a vice-president of Todd, and Todd responded to that communication on October 2, 2006.  Ms. Miles rejected Todd’s appeal on April 25, 2007.  The negative evaluations were then made part of the Construction Contractor Appraisal Support System (“CCASS”).

The government’s motion to dismiss contented that the Court lacked jurisdiction because Todd’s challenge to the accuracy and procedural propriety of performance evaluations was not a “claim” within the meaning of the Contract Disputes Act because it is not made “as a matter of right” and does not arise from or relate to the contract. Specifically, the government contended that [w]here, as here, the contractor’s claim is that the Government breached its internal policies, rather than the provisions of the contract, such a claim cannot properly be considered a claim ‘relating to the contract.’” The Court disagreed and concluded that “this is a ‘final decision’ of the contracting officer upon a ‘written demand,’ and the Court further concluded that Todd made that written demand ‘as a matter of right.’” 

The Court further stated that Federal regulations require that for construction contracts the “contracting activity shall evaluate contractor performance and prepare a performance report” “in accordance with agency procedures,” and that the report must be “reviewed to ensure that it is accurate and fair.” FAR 36.201.  The Corps has set forth detailed procedures to be followed in assessing contractor performance, with additional steps to be taken when the rating will be unfavorable.  Army Corps of Engineers Regulation 415-1-17(5)(c)(1).  In this case, Todd alleges that those procedures were not followed and that the evaluations it received were not, in fact, accurate and fair.  To the extent plaintiff asserts that when the Government prepares a performance evaluation that will be made part of the record upon which its future submissions will be judged, it is entitled to an accurate and fair performance evaluation prepared in accordance with the regulations, it makes that request “as a matter of right.” Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1265 (Fed. Cir. 1999) (observing that the “claim must be a demand for something due or believed to be due rather than, for example, a cost proposal for work the government later decides it would like performed”); BLR Group of Am. v. United States, No. 07-579C, at 10 (Fed. Cl. Nov. 25, 2008).

While the Court has scheduled further briefing by the parties as to what should be the appropriate remedy, the decision comes as yet another welcome advance in the willingness of the Court to look into the fairness of contractor performance evaluations. In the past, government agencies have acted with impunity and have leveraged their power to issue poor performance ratings in order to extract concessions from contractors during performance. There is no question, moreover, that the power to reduce a performance rating has had a chilling effect on the filing of claims – a right that is granted by law and regulation. The Court further noted that “the creation of mandatory performance reviews, databases archiving those reviews, and the requirement to consider those archived materials in future contract awards means that a negative review is potentially devastating to a contractor, who may have no opportunity—or very little opportunity—to mitigate the impact that review will have on future awards.”  Accordingly, “there are sound reasons, as Judge Sweeney recently explained, to address performance evaluations as issues of contract performance rather than as part of a bid protest when the contractor seeks future government contracts.”  See BLR Group of Am. v. United States, No. 07-579C, at 17 (Fed. Cl. Nov. 25, 2008).

The BLR and the Todd cases make it clear that contractors do not have the right to simply challenge a performance evaluation by filing an appeal directly to the Court. There must first be a “claim” that is submitted to the contracting officer challenging the decision and explaining why the contractor believes that the performance rating should be changed. If the contracting officer then issues a decision denying the “claim,” or if the contracting officer fails or refuses to respond within a reasonable time, the contractor may then appeal the contracting officer’s decision to the Court of Federal Claims. (The jurisdiction of the boards of contract appeals is not as broad as the Court’s and the boards have not been as receptive to contractor challenges to performance evaluations). Because this is an evolving area of the law, however, and because there are procedural hurdles that must be overcome, it is strongly suggested that contractors seek legal counsel before undertaking an appeal of this nature.

Method of Calculating Recovery Of Extended Home Office Overhead

In a decision earlier this month, the Armed Services Board of Contract Appeals reiterated that the recovery of unabsorbed home office overhead, based on the Eichleay formula, is for "a stand-by of an uncertain duration." The Board held that where a contractor is entitled to a compensable contract time extension for additional work, the contractor is entitled to recover extended home office overhead.  Extended home office overhead is calculated as a fixed percentage markup of costs incurred during the contract time extension. Fru-Con construction Corporation, ASBCA No. 55197, 55248, October 4, 2007. For a discussion on the Eichleay formula and the recovery of unabsorbed home office overhead, see our earlier article.

Important New Rules on Electronically Stored Information

On December 1, 2006, amendments to the Federal Rules of Civil Procedure became effective and made something that had already been established by court decisions very clear – that virtually every kind of electronically stored information (“ESI”) is discoverable in litigation.  Government construction contractors, and their attorneys, need to be concerned about the preservation and disclosure of electronic information, including e-mail messages, voicemail messages, and any kind of a file stored on a computer.  Unfortunately, as the information age makes an exponentially greater volume of information available, the seemingly easy storage of that information may actually be creating a vast minefield for the unwary.

Contractors need to be aware that even computer files that have been intentionally or inadvertently deleted are potentially discoverable.  (Simply because data has been “deleted” from a hard drive does not necessarily mean that it cannot be retrieved).  Courts may no longer accept the excuse that “the files were erased” if there was an obligation to preserve the data, or if the company failed to have an established ESI retention policy to assure the reasonable retention of electronic information.  The new rules provide guidance and clarification on a number of topics related to electronic discovery (e-discovery), including the discoverability of data that is difficult to access, such as back-up tapes, the form in which electronically stored information should be produced, and how to deal with the inadvertent production of privileged information when large amounts of electronic data are produced.

One of the difficulties with the production of electronic data is that it is often harder to review than paper documentation because it involves the examination of large amounts of data stored on CDs, DVDs, floppy disks, hard drives, backup tapes, network servers, Internet backup services, and other storage devices.  A company often finds it to be an overwhelming task to gather the data, and an equally daunting and costly task to electronically produce it.  Electronic information on a complex matter involving technical data can occupy hundreds or even thousands of CDs (we are currently involved in exactly such a case). 

It is important to recognize that the content of electronic information can be very different, and far less formal, than paper documentation.  We have noticed that there is often a tendency to be careless when writing an e-mail message because of the informality, as compared to a letter.  Contractor personnel are frequently very candid in e-mail messages and they may make off-the-cuff remarks that give the other side “ammunition” to discredit the contractor’s position.   In addition, electronic information often contains “metadata” (underlying data that states when a document was created, modified, accessed, etc.).  Without realizing it, or intending to do so, an electronic file may provide much more information than the author or the company ever intended, or was required, to preserve and that information may be a goldmine for the other side in litigation.

Continue Reading...

Task Order Contractors Must be Given a Fair Opportunity to Compete for Individual Task Orders

As we have mentioned previously, the growing use of multiple award task order contracts in federal construction contracting, as can be seen in much of the disaster recovery work in New Orleans, is limiting the competitive opportunities for small and mid-sized construction contractors.  Unless a contractor is the recipient of one of the major task order contract awards, there is no opportunity for a contractor to compete for upcoming individual task orders and the contractor is effectively precluded from competing for potentially millions of dollars of work to be awarded over a period of years. In the past, when there were more single award contracts, if a contractor lost out to a competitor, there was always another solicitation on the horizon.  If a contractor fails to become one of those selected to compete under a multiple award task order contract, there may be no, or very little, work “waiting in the wings.”

It follows that it is important to monitor the decisions of the GAO and the courts to see what is being done to protect the rights of contractors, and we will continue to do so.  In a newly issued GAO decision, Palmetto GBA, LLC, B-299154, December 19, 2006, the Comptroller General stated that according to the legislative history of the Federal Acquisition Streamlining Act (FASA), task and delivery-order contracts were intended to encourage the use of multiple-award, rather than single-award contracts, in order to promote an ongoing competitive environment in which each awardee would be fairly considered for each order issued.  H.R. Conf. Rep. No. 103-712, at 178 (1994), reprinted in 1994 U.S.C.C.A.N. 2607, 2608; S. Rep. No.103258, at 15-16 (1994), reprinted in 1994 U.S.C.C.A.N. 2561, 2575-76. In this regard, the Federal Acquisition Regulation (FAR) requires agencies to provide all awardees “fair opportunity to be considered for each order exceeding $3,000 issued under multiple delivery-order contracts or multiple task-order contracts.”  FAR sect. 16.505(b)(1)(i).

An interesting aspect of the Palmetto case is that the GAO reiterated that a task or delivery order that precludes competition for future task or delivery orders for the duration of the contract performance period may constitute a “downselection.”  The GAO has recognized downselections in circumstances not only where all work under a contract will be foreclosed from future competition, but also where specific categories of work will be similarly foreclosed for the duration of the contract.  While the GAO did not find that “downselection” occurred in the Palmetto case, it is important for contractors to recognize that a task order award that eliminates competition for future work can be successfully protested. Continue Reading...

Declining Opportunities for Small and Mid-Sized Federal Construction Contractors

The cover story, “New Marching Orders,” in the most recent edition of Constructor, published by McGraw-Hill Construction, highlights a trend in military construction that should concern small to mid-size general contractors.  In the past, many projects for construction of military housing and other facilities were procured as individual contracts through sealed bid solicitations issued by the U.S. Army Corps of Engineers.  Small and mid-size contractors, familiar with the local market conditions, were well positioned to compete for, win, and perform these contracts.  E. Michael Powers reports that today, however, the Corps is focusing its procurement efforts on multiple-award construction contracts and indefinite delivery/indefinite quantity contracts with task orders.  These contracts tend to be for greater volumes of work, resulting in contracts that exceed the bonding capacity of many small to mid-size firms.

Powers also notes that a contract to build fifty buildings at a cost of $10 million per building, spread across a large geographic area, might not even appeal to firms that have the bonding capacity to bid on such a large contract.  In addition, where so much work is included in one contract, there is only one prime contractor, whereas before there could have been as many as fifty contractors performing fifty separate projects.

These large procurements are often the subject of negotiated procedures under FAR, Part 15, where price is no longer the controlling factor in determining who receives the contract.  In these "best value" procurements, the experience and past performance of a larger contractor may be decisive in the Corps' award decision.

Continue Reading...