November 2006

The Baltimore District, in conjunction with the Society of American Military Engineers, is conducting a one-day forum on the workload created by the Base Realignment and Closure (BRAC) construction program in the District.  This multi-billion dollar program includes new construction and renovation work.  The forum will be held on December 7, 2006 in Hunt Valley,

This recent Court of Federal Claims decision involves a USDA contract for the construction of a vegetable laboratory in Charleston, South Carolina. The contractor was terminated for default and the bonding company, Travelers Casualty and Surety of America, took over under the terms of the performance bond. 

While there is nothing particularly noteworthy about the Court’s lengthy recitation of the facts, the Court did restate some important rules governing the determination of defective specifications. The Court referred to one of the landmark cases in federal government contracting, Spearin v. U.S., where Justice Brandeis wrote the Supreme Court opinion that established the “Spearin Doctrine’ (a contractor will not be liable to an owner for loss or damage which results solely from insufficiencies or defects in plans and specifications). As the Supreme Court explained:

[I]f the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work . . . . In Spearin, the Supreme Court held that contract provisions “prescribing the character, dimensions and location of” a structure to be constructed “imported a warranty that, if the specifications were complied with, the [structure] would be adequate.”

Continue Reading A Contractor is Not Liable for the Consequences of Defective Specifications

This article describes a GAO decision that highlights how difficult it is to prevail on a protest that challenges an agency’s rating of a proposal where the protest is not supported by anything more than a difference of opinion as to how much weight, or what score, should be assigned to a particular evaluation factor. Absent a showing that there was no rational basis for an agency’s evaluation, contractors should not expect the GAO to overturn an evaluation.

The GAO published a decision today that was originally issued on July 19, 2006, but delayed in being made public because of the need for redactions.  The case involved a protest by East-West Industries, Inc. against the award of a contract to Regent Manufacturing, Inc.   The solicitation was issued under request for proposals (RFP) No. FA8518-04-R-70801, advertised by the Department of the Air Force for multi-aircraft canopy cranes (MACC). East-West challenged the past performance and risk evaluations of its and Regent’s proposals. The protest was denied.

In its decision, East-West Industries, Inc. , B-297391.2; B-297391.3, the GAO stated that in reviewing a protest of an agency’s proposal evaluation, “our review is confined to determining whether the evaluation was reasonable and consistent with the terms of the solicitation and applicable statutes and regulations.” The GAO found that the evaluation of protester’s proposal under the past performance evaluation factor was unobjectionable where the agency reasonably concluded that only one of four prior contracts was of a magnitude and complexity essentially the same as the solicitation’s, and thus met the solicitation’s definition of very relevant. Since only one contract was rated very relevant and the protester received exceptional performance ratings under only two of its three relevant contracts, the GAO determined that the agency reasonably concluded that East-West’s performance record warranted assigning the firm a very good/significant confidence rating based on there being little doubt–rather than no doubt–as to its successful performance.Continue Reading It is Difficult to Successfully Challenge an Agency's Past Performance and Risk Evaluation

The Navy recently awarded three cost-plus-award-fee, indefinite-delivery/indefinite-quantity (ID/IQ) contracts to Fluor International, Inc., URS-IAP, LLC (a joint venture of URS Corporation and IAP Worldwide Services, Inc.) and Atlantic Contingency Constructors, LLC (a limited liability company managed by The Shaw Group) for global contingency construction. Each contract was for a base year with four one year options, and the value of each contract was approximately one billion dollars. The contractors were to provide construction and related engineering services in response to war fighting needs, global natural disasters, and humanitarian assistance.

The awards were made following a "best value" evaluation based on experience, past performance, contingency planning, management, small business utilization, and cost. Non-cost factors were considered more important than cost. A disappointed offeror, Kellogg Brown & Root Services, Inc. (“KBR”), filed a GAO protest asserting that the Navy misevaluated the proposals under technical and cost factors. The GAO agreed and issued a decision sustaining the protest.Continue Reading GAO Recommends Navy Return To Square One in Award of Billion Dollar Contracts

A GAO decision released today, but dated November 15, 2006, reported that Advanced Federal Services Corp. protested the award of a contract to Eastek, Inc. under request for proposals (RFP) No. W9128Z-06-R-0001, issued by the Department of the Army Communications-Electronics Life Cycle Management Command for business administrative support services (BASS).  The protester contended that

The GAO published a decision today in the Matter of SunEdison, LLC, B-298583; B-298583.2, dated October 30, 2006, involving SunEdison’s protest of an award to PowerLight Corporation under request for proposals (RFP) No. FA4861-06-R-B501, issued by the Department of the Air Force for the construction and operation of a photovoltaic array to supply solar power to Nellis Air Force Base (AFB) in Nevada. The protester contended that the agency’s evaluation of offerors’ prices was flawed and the GAO sustained the protest.

The protester argued that the agency’s evaluation of the offerors’ prices was flawed in that it failed to take into consideration that PowerLight’s price was offered contingent upon “successful completion of an REC purchase agreement with Nevada Power,” whereas its own price was offered on an unconditional basis.  The GAO agreed that the agency’s price evaluation was flawed and found hat PowerLight’s inclusion of a contingency in its pricing rendered the proposal ineligible for award.  Where a solicitation requests offers on a fixed-price basis, an offer that is conditional and not firm cannot be considered for award.  Omega World Travel, Inc.; Sato/Travel, Inc., B-288861.5 et al., Aug. 21, 2002, 2002 CPD para. 149 at 6.  Here, not only did PowerLight make its offer conditional upon successful completion of an REC purchase agreement, but further, it acknowledged the uncertainty of such an agreement being reached.

Government contractors need to keep in mind, when responding to a sealed bid invitation or to a request for proposals, that conditional pricing is an almost certain way to have your bid, or offer, rejected.  Of course, this procurement seems to have been yet another of those all too frequent “negotiated” procurements were actual discussions, or negotiations, did not occur. The Contracting Officer simply furnished each of the offerors with “evaluation notices” describing required information that had not been fully addressed in the proposal or that required clarification.  Apparently the uncertainty in PowerLight’s proposal was not addressed, and there were no discussions during which additional issues could have been raised. (Unlike sealed bidding, where a bid cannot be revised after bid opening, offers submitted in response to a Request for Proposals can be revised after offers are submitted if the government conducts discussions, or negotiations, and gives the offerors in the competitive range an opportunity to submit best and final offers. The regulations regarding Contracting by Negotiation are found in FAR, Part 15).Continue Reading Protest of Agency’s Flawed Evaluation of Awardee’s Conditional Pricing Sustained by the GAO

The Office of Federal Contract Compliance Programs (OFCCP) has published a Technical Assistance Guide designed to help federal government construction contractors and subcontractors comply with the federal laws and regulations that prohibit government contractors from discriminating in employment, and require that they undertake affirmative action to ensure equal employment opportunity in their workforces.  It is intended for government contractors who have construction contracts and/or subcontracts.  The obligations of government contractors and subcontractors who hold non-construction contracts differ in significant ways and are covered in a separate guide.

This Guide does not create new legal requirements or change current legal requirements. Instead, it reflects the views of OFCCP and is intended to serve as a basic resource document on OFCCP-administered laws. The legal requirements related to equal employment opportunity that apply to Federal supply and service contractors are contained in the statutes, executive orders, and regulations cited in the Guide. Every effort has been made to insure that the information contained in the Guide is accurate and up to date.Continue Reading Technical Assistance Guide for Federal Construction Contractors

A new regulation announced by the Small Business Administration on November 15, 2006, to be effective on June 30, 2007, requires small businesses to recertify their size when they are purchased by or merged with a larger business, or at the end of the five-year point of a contract.  The rules are intended to help small businesses obtain more federal contracts and to assure that contracts set aside for small businesses are not going to larger companies.  As reported in the Thompson West publication, the Government Contractor Online Update, “According to SBA Administrator Steven Preston, the changes “will go a long way toward ensuring that contract awards get in the hands of small business owners, federal agencies get the proper credit toward their small business contracting goals and small business contracts are fairly and accurately reported..’”

There are critics of the new policy, however, who contend that the SBA has not gone far enough to prevent larges businesses from intruding into the small business marketplace.  The American Small Business League has commented that “A new policy proposed by the Small Business Administration (SBA) and the Office of Federal Procurement Policy (OFPP) will allow the government to continue reporting awards to large companies as federal small business contracts.” (See the full article).

Pertinent parts of the new regulation are as follows:Continue Reading New SBA Regulations Require Small Businesses to Recertify After Five Years

The U.S. Army Corps of Engineers awarded an $88 million contract for the construction of a fifty-three mile road around a tropical island in the North Pacific. During contract performance, the contractor submitted a certified claim contending that the contract clause, "Time Extensions for Unusually Severe Weather," was defective, resulting in a gross misrepresentation of the number of adverse weather days that could be anticipated during performance of the work.  The contractor also contended that reliance on the defective specification led to an increase in the cost to perform the work. The certified claim included costs incurred up to the date of the claim submission and costs estimated to be incurred in the future.

The United States Court of Federal Claims found that $50 million of the contractor’s certified claim of $63.4 million was clearly fraudulent. During the trial, witnesses, including the corporate officer who certified the claim, testified that the $50 million claim "was a means to get the Government’s attention, and to show the Government what would happen if it did not approve the new compaction method that plaintiff wanted."  The Court stated that this part of the certified claim was not submitted in good faith, and was not for an amount which the Plaintiff honestly believed it was entitled. Daewoo Engineering and Construction Co., LTD. v. U.S., No. 02-1914C, October 13, 2006.  Accordingly, the projected additional costs based on estimates, and not yet incurred, were found to be fraudulent.Continue Reading Contract Claim Designed to "Get the Government"s Attention" Found to be Fraudulent